Inglewood Water Main Extension - Construction Update
We are continuing our work to replace and extend the water main on 12 Street SE between 8 Avenue SE and 11 Avenue SE. The schedule for the final work phases (5 and 6) along 12 St SE between 9 Ave SE and 11 Ave SE have been adjusted slightly. We apologize for any inconvenience this may cause and thank you in advance for your patience and cooperation.
Construction Schedule
The work will be phased to ease traffic impacts.
Phase 4: 12 Street SE between 9 Avenue & 11 Avenue SE, currently in place
Work is ongoing and set to be completed on June 15th.
Southbound lane on 12 St SE between 9 Av SE and 11 St SE closed to vehicle traffic.
Southbound traffic to be detoured using 11 Street SE.
One lane northbound traffic to be maintained.
Phase 5: 12 Street SE between 9 Avenue & 11 Avenue SE
Work is scheduled to begin on Saturday June 8 to Tuesday, June 11.
Westbound traffic on 9 AV SE will be maintained during these dates.
Eastbound traffic of 9 Av SE will be detoured to 8 Av SE. between 11 St. and 13 St.
Southbound traffic from the Zoo St. bridge on 12 St SE will be detoured to 8 Av SE.
Southbound traffic, South of 9 Av. SE will be detoured to 11 St. SE
South side of 9 Av SE will be closed for construction.
Traffic accommodation: Lane closure on 12 St. SE will be removed on Friday, June 7, to allow for two lanes of traffic on 12 St. SE to ensure there will be no impact to the Inglewood Night Market. Closure will be put back in place at 5 a.m. on Saturday, June 8 until Tuesday, June 11.
Phase 6: 12 Street SE between 10 Avenue SE and 11 Avenue SE
Work is scheduled to begin on Sunday, June 16 to Sunday, June 30.
Two-way traffic along 12 St SE. will be shifted to the west side of 12 St.
There will be no access to 12 St SE from Westbound 10 Av SE.
There will be no impacts to 9 Ave. traffic
Construction Impacts
Temporary water service, and possible water shut offs for nearby buildings.
Temporary street parking restrictions and/or closures.
Vibrations due to compaction.
Additional traffic and congestion due to construction activities and vehicles; in particular, impact to accessing parts of back lanes.
Regular hours will be 7 a.m. to 7 p.m. Monday to Saturday
Temporary Water Service
During construction, some residents and businesses will be provided a temporary water supply, and access to your property will be required. Before construction starts, a contractor representative will request entry to your property.
Please note that internal fire suppression systems will not work if a building is being supplied by temporary water services.
Should it be necessary to disrupt water service, all affected customers will receive notice at least a day in advance.
Project Information or Questions
For more information about this project, call 311 and reference the Inglewood Water Main Replacement Program.