Construction Update: Inglewood Sanitary Trunk Phase Two
Phase Two of the Inglewood Sanitary Trunk (IST) project is underway, with the full project anticipated to be complete by July 2025.
Construction Schedule
Completed Work
The microtunnelling work on the south side of the river has been completed.
Mid-October – Mid-November
The intersection at 8 Ave SE and 9 St SE continues to be closed until early November while our crews connect to the Inglewood Sanitary Trunk and existing Inner City Trunk.
Crews are currently onsite to complete Inner City Trunk Cleaning along 8 Ave SE between 8 St SE and 15 St SE
No street parking along 8 Ave SE between 8 St SE and 15 St SE between 7 am and 9 pm Monday-Friday during cleaning. Duration for each section of sanitary cleaning (street block) is anticipated to take approximately one week.
Crews working in the green space are working on installing the connection pipes.
Late 2024 to Mid 2025
Crews will continue to work on installing the connection pipes, site restoration and plantings.
Crews will also be working on the northside of the river to connect to a sanitary trunk that runs underneath Memorial Drive
Construction Impacts
On-site construction activity including construction crews, vehicles, and heavy equipment.
Noise, vibrations and dust. Noise levels will be monitored.
Limited on-street parking to assist Inner City sanitary cleaning crews.
Open sewer work leading to an odor in the community.
Cleaning work from 7 am to 9 pm
Detours
Pedestrian, pathway and vehicle detours will be in place at 8 Ave SE for the remainder of this project. For the most up-to-date detour information related to this project, please visit www.calgary.ca/ist.
Pathway detour information can always be found at maps.calgary.ca/PathwaysandBikeways
We thank residents for your patience and understanding while we complete this necessary work.
Project Information or Questions
If you have any questions about this work or the project please contact 311, visit Calgary.ca/ist for more information.