Ogden Dale Road SE upgrades
On May 15, Green Line activities related to the 78 Avenue Project will require the closure of EVRAZ’s existing entrance to upgrade Ogden Dale Road SE. EVRAZ will install a new entrance just east of the existing entrance to ensure no interruption to operations.
What is the work?
Green Line roadworks on Ogden Dale Road SE in front of EVRAZ.
This is a phased project that requires the closure of EVRAZ’s entrance at Ogden Dale Road SE.
Starting May 15 for two weeks: Installation of manhole just south of Ogden Dale Road SE. Equipment will be stored near the corner of Ogden Dale Road for mobilization to site.
Starting early June for 6 weeks - Ogden Dale Roadworks Stage 1: closure of the west lane of Ogden Dale Road SE for roadworks removals, existing catch basin removals, installation of new catch basins and road structure, paving of new road.
Mid-July for 4 weeks - Ogden Dale Roadworks Stage 2: closure of the east lane of Ogden Dale Road SE.
Mid-August: Toplift paving
Mid-August for three weeks: Ogden Dale Road SE retaining wall and asphalt pathway installation.
Temporary fencing will remain in place for the duration of the project followed by permanent fence replacement.
For more information or if you have any questions, please email the project team at greenline@calgary.ca