42 Avenue Complete Streets Project Update
As previously communicated, remaining construction was substantially completed in fall 2021, including Ongoing work has been happening along 42 Avenue SE between 1A Street SW and 12 Street SE to improve the walking. biking, and transit experience and provide better access and connections in the area. The bulk of the work has been completed, including the build-out of missing sidewalk links along 42 Avenue SE. and the multi-use pathway along 12 Street SE.
While initially scheduled for 2022, traffic and pedestrian signal upgrades at the intersection of 42 Avenue and 1 Street SE have been delayed, and are now expected to take place in spring 2023. Following completion of this work, the temporary pathway tie-in on the north side of the intersection, over the CP Rail crossing, will be replaced with permanent material.
Landscaping maintenance was completed in spring & summer 2022 and will continue through 2023 as required.